Opportunities to Do Business with the Universities

Construction Solicitations to Prequalify Contractors

Full Details

 Institution NC State University 
 Institution URL for Additional
Information about this Project (Optional)
 https://facilities.ofa.ncsu.edu/2026/03/request-for-general-contractor-prequalification-submittals-ligon-st-beryl-rd-water-line-improvements/ 
 Project Name Ligon St -Beryl Rd Water Line Improvements - I-440 Widening 
 Prequalifying for 
This project improves the domestic water service to the Horticultural Field Labs (HFL) and the Dearstyne Complex by extending a new water line service and connection from Beryl Road and by installing a loop connection in existing piping serving the Dearstyne Complex. The project will also address domestic water pressure issues experienced by the HFL since the West Campus was disconnected from the Method Road pumping station as a result of the I-440 widening.
 
 Main Contact for Submission Campus Contact 
 Name of Design Firm RMF Engineering 
 Design Firm Contact Name Daniel Craig 
 Design Firm Telephone Number (919) 941-9876 
 Design Firm Email daniel.craig@rmf.com 
 CM at Risk Firm Name  
 CM at Risk Firm Email  
 Campus Contact Email David Hammock 
 Due Date 04/17/2026 
 Due Time 5:00 pm 
 Submit To 
Receiving Email Submissions Only: DC_Formal_Prequal@ncsu.edu NC State University David Hammock, PE Project Manager NC State Design and Construction Email for questions only: david_hammock@ncsu.edu