  https://fac.uncg.edu/wp-content/uploads/20260121_Quad-Duct-Bank_Ad4Designer.pdf 
  Quad Duct Bank - Emergency Generator Connection 
  Architectural/Engineering 
  Bill Chatfield 
 Phone Number 
(404) 550-2060
 
  wjchatfi@uncg.edu 
  02/24/2026 
  
$2,655,000
 
  One-Two Sentences
The project scope is to install the duct bank life safety and optional standby power systems from the Weil/Winfield generator to the seven (7) residence halls in the Quad (Jamison, Coit, Bailey, Cotten, Hinshaw, Gray, Shaw). Scope of work includes disconnects, transfer switches, panels, etc. at the buildings. The generator was installed in 2019 and was sized to accommodate the additional load required. Designer is to provide the least intrusive practical design. Construction completion is to be scheduled no later than July 23, 2027.
 
  (Contact Person, Name of Institution & Address)
Letters of Interest must be submitted electronically in PDF format no later than 12:00 pm (Noon), February 24, 2026. Submit Letters of Interest to: Bill Chatfield UNC Greensboro Facilities Design & Construction fdc@uncg.edu
 

In order to offer architectural or engineering services in response to this solicitation, the proposer must be licensed in the State of North Carolina.