Construction Solicitations to Prequalify Contractors
Full Details
Institution | NC State University | |||
Institution URL for Additional Information about this Project (Optional) | https://facilities.ofa.ncsu.edu/category/ads/ | |||
Project Name | Steam Repairs Phase VIIIC | |||
Prequalifying for | North Carolina State University is seeking qualification
statements from general contractors for improvements to
Steam Repairs Phase VIIIC, located on North Campus. This
project will complete upgrades to the steam and condensate
piping in the North Campus walkable steam tunnel, trench and
mechanical rooms of DH Hill Library. The scope includes
asbestos abatement of all insulation around existing steam
pipe; removal of the 30 psi steam pipe and associated
condensate pipe; removal of the existing Pressure Reducing
Valve (PRV) station that was installed as part of the
previous phase and reuse some of the valves and fittings;
removal of the existing hangers for the pipes along the
walkable tunnel; excavation of the area over the trench
located south of the Atrium; installation of new 150 psi
steam pipe and condensate pipe; installation of new
structural supports including anchors and guides for the
steam and condensate lines; installation of new insulation
around the new 150 psi steam pipe; building and installation
of new PRV stations in the mechanical rooms to convert the
incoming 150 psi steam to 30 psi steam; installation of taps
on the tunnel steam and condensate pipes to allow for use in
future buildings adjacent to the site. The construction is
expected to be done in two phases: the North-South walkable
tunnel in summer 2019, and the East-West trench and building
interior work in summer 2020. | |||
Main Contact for Submission | Campus Contact | |||
Name of Design Firm | RMF Engineering | |||
Design Firm Contact Name | Jonathan Eveleth | |||
Design Firm Telephone Number | (919) 941-9876 | |||
Design Firm Email | jonathan.eveleth@rmf.com | |||
CM at Risk Firm Name | ||||
CM at Risk Firm Email | ||||
Campus Contact Email | llzaytou@ncsu.edu | |||
Due Date | 11/16/2018 | |||
Due Time | 3:00 pm | |||
Submit To | NC State University
Laura L Zaytoun
Capital Project Management
2701 Sullivan Drive, Suite 331
Campus Box 7520
Raleigh, NC 27695-7520
Phone: 919-515-8049 |