Construction Solicitations to Prequalify Contractors

Full Details

 Institution NC State University 
 Institution URL for Additional
Information about this Project (Optional)
 https://facilities.ofa.ncsu.edu/category/ads/ 
 Project Name DH Hill Towers and Poe Hall Waterproofing Project 
 Prequalifying for 
The DH Hill North Tower, the DH Hill South Tower, and the Poe Hall Exterior are all experiencing waterproofing and leaking issues at expansion joints, control joints, windows, doors, masonry-to-masonry joints, and masonry-to-metal joints. This project will remove all existing caulking and backer rods from these interfaces, clean all surfaces of dirt, paint, and oils, prime all joints, seal all interfaces, re-caulk all interfaces, reseal all joints and seams, and repoint masonry where necessary.
 
 Main Contact for Submission Campus Contact 
 Name of Design Firm SKA Consulting Engineers 
 Design Firm Contact Name Kirk Stanford 
 Design Firm Telephone Number (919) 855-0993 
 Design Firm Email Kastanford@skaeng.com 
 CM at Risk Firm Name Not Applicable 
 CM at Risk Firm Email Not Applicable 
 Campus Contact Email srbostia@ncsu.edu 
 Due Date 01/26/2018 
 Due Time 5:00 pm 
 Submit To 
Steven R. Bostian, PE North Carolina State University Capital Project Management Administrative Services III Building 2701 Sullivan Drive Raleigh, NC 27695-7520 Please go to the NC State University webpage for further information. The electronic pre-qualification file will be available on or after January 4, 2018 by contacting Steven Bostian, the NC State Project Manager at 919-515-8059 or via email at srbostia@ncsu.edu.