| Project Description | | One-Two Sentences
Pre-Proposal Meeting: April 26, 2016 at 239 Jackson Circle
in Chapel Hill at 10am, Odum Village.
The demolition at Odum Village is necessary for future
campus development. The two story buildings were constructed
in the early 1960's and include three building types,
four units, six units, and eight units. The (36) buildings
are approximately 192,500 gsf and are used for coed
undergraduate housing. Abatement for lead and asbestos will
be required on all buildings, as well as roadway, parking
lot, and underground utility removal. The demolition work is
expected to be performed in phases to accommodate the
continuous use of (6) other buildings for non-residential
purposes in the vicinity. | |