Project Name | CCUP Chiller Plant Capacity Expansion | |||
Prequalifying for | North Carolina State University is seeking qualification
statements from general contractors for the Centennial
Campus Utility Plant Chiller Plant Capacity Expansion. This
project will increase the chilled water generation capacity
at the Centennial Campus Utility Plant. The project will
include installing a 2,000 ton chiller, a 3,000 ton cooling
tower, and all auxiliaries to support the chiller
installation.
To qualify, the contractor must have a general
contractor's license in the State of North Carolina as
well as meet applicable bonding requirements. The
contractor must show comparable work experience, both in
complexity and dollar value, and preferably in a University
campus environment, to the scope of work outlined above.
| |||
Main Contact for Submission | Campus Contact | |||
Name of Design Firm | RMF | |||
Design Firm Contact Name | Mike Raabe | |||
Design Firm Telephone Number | ||||
Design Firm Email | mike.raabe@rmf.com | |||
CM at Risk Firm Name | ||||
CM at Risk Firm Email | ||||
Campus Contact Email | david_hammock@ncsu.edu | |||
Due Date | 06/24/2013 | |||
Due Time | 5:00 pm | |||
Submit To | David Hammock
North Carolina State University
Capital Project Management
Administrative Services III, Suite 331
2701 Sullivan Drive
Campus Box 7520
Raleigh, NC 27695-7520
919.515.2030
david_hammock@ncsu.edu |